Corridor ManagementRoad rehabilitation programme
GOMBAK - MENTAKAB · 100 KM CORRIDORRoad Rehabilitation Digital TwinSIMULATED PROPOSAL ENVIRONMENT
Cesium scene connected Proposal demonstrator
PHYSICAL PROGRESS47.2%Planned 53.6%
COMPLETED18.4 km100 km corridor
ACTIVE WORK ZONES31 critical delay
ASPHALT PLACED3,432 tSimulated quantity
CERTIFIED VALUERM 4.82m18.7% of works
CESIUM 3D WORKSITE · SIMULATED
Active resurfacing zone
KM 42+300 - KM 43+150
Constructing Cesium worksiteLoading terrain, corridor geometry and physical roadwork assets
Illustrative prototype. Alignment, chainage, quantities and progress are simulated and not for construction or measurement.
REPAIR PLAYBACKAsphalt laid
68%SIMULATED